Start with the actual problem
Factory Acceptance Testing and Site Acceptance Testing answer different questions. FAT provides evidence about equipment and functions that can be tested before shipment. SAT tests the installed system within its real utilities, interfaces, site constraints and operating organization. Neither should be confused with a full guarantee of long-term production performance.
Establish an evidence-based baseline
Build traceability from requirements to test cases. At FAT, verify documented functions, logic, representative material handling, configuration and key alarms using the facilities available. State explicitly which customer conditions are simulated and which are deferred to site. Observation and documentation must be interpreted together. A drawing can show intended arrangement, while operational records and site verification reveal how the system is actually used. Where the two disagree, the difference should remain open until resolved.
Build the engineering approach
At SAT, verify interfaces with actual machines, infrastructure, network behavior, physical transfer, safeguards, fault recovery and required production scenarios. Define tolerances, number of cycles or observation windows as appropriate for the application, avoiding arbitrary pass thresholds. Commissioning should be planned as a sequence of verifications rather than a single event. Mechanical completion, utilities, functional checks, interface tests, safety validation by competent personnel, realistic production trials and handover are distinct. Each needs its own evidence and acceptance boundary. A signed checklist cannot compensate for a missing test; equally, a fault found during a controlled trial is useful information if it is recorded and resolved. Operators and maintainers should participate before the system is released for routine use.
Examine the critical technical details
Maintain a defect and exception protocol. Every deviation needs severity, owner, correction plan and retest evidence. Define how conditional acceptance works and which open items prevent safe operation or contractual completion. A verbal agreement during a test is insufficient change control. Delivery and lifecycle work are defined by evidence and operational ownership. A milestone is meaningful only when the prerequisites and acceptance criteria are clear. Commissioning records, support paths, training and change histories should stay useful after the project team leaves. A technical issue may belong to hardware, configuration, infrastructure or procedure; disciplined coordination prevents these differences becoming unresolved supplier disputes.
Make tradeoffs visible
The tradeoff is test coverage versus available time. Critical safety and functional cases cannot be sacrificed to improve schedule appearance. Less important endurance trials can sometimes be planned as controlled post-acceptance monitoring if this is explicitly permitted in the agreement. The important question is not whether a tradeoff can be eliminated altogether. It is whether it is understood, accepted by the right decision-maker and reflected in the resulting requirements, test scope and support plan.
An illustrative industrial situation
Illustrative scenario: a robotic pallet transfer passes FAT with a simulated conveyor. At SAT, the live conveyor sends its ready signal late under peak conditions. The site team tests state transitions, timeouts and recovery, and records a joint fix instead of declaring either vendor’s equipment defective by assumption. This is a hypothetical engineering scenario, not a claim about a ČAMINSKI customer, a named manufacturer or a measured commercial result. Its purpose is to show how the order of questions can change the quality of the final decision.
What should be verified
Evidence includes signed protocols, equipment identifiers, software versions, witnessed results, deviation logs, outstanding items, training confirmation and handover criteria. Operational-readiness review should additionally consider support, spares, ownership and shift procedures. Evidence should be stored with context: who observed it, the equipment or facility condition under which it was collected and the version of the relevant drawing or software. If a test fails, retain the record and define a retest instead of quietly replacing the original result.
Typical mistakes to avoid
Avoid using a supplier demonstration as FAT, repeating identical tests at site without checking actual interfaces and treating punch lists as informal notes with no closure owner. The most dangerous omissions are often presented as small assumptions. Treat each unresolved item as either a verified constraint, a planned test or a clearly accepted risk. It should never disappear merely because the presentation has moved to the next stage.
The decision that should follow
Well-planned FAT and SAT reduce ambiguity. They make clear what was proven, under what conditions, and what still needs attention before the system is relied upon by production. Where the next action involves changes to machinery, control systems or work practices, assess the applicable safety, contractual and competence requirements with the responsible parties. A blog article can explain good engineering discipline; it cannot replace project-specific verification.
A second perspective for the project team
For lifecycle performance, a verified improvement requires a stable baseline, controlled change and sustained observation. A single successful run is useful test evidence, not proof that an operational issue has been permanently eliminated.
A practical decision checkpoint
Before a delivery stage is called complete, ensure the next team knows the outstanding issues, approved configuration, evidence of tests and limits of the acceptance. A project handover is an exchange of operational responsibility, not merely documents.
Before the team proceeds, it helps to ask a few concrete questions rather than reviewing only technology specifications or status slides:
- Which conditions are simulated at FAT?
- Which are site-specific?
- What is a blocking defect?
- Who signs operational handover?
- Which prerequisites must be demonstrated before the next stage?
After go-live, revisit the outcome under comparable demand and operating conditions. Document changes and keep the supplier or competent engineer involved where interfaces, safety or validated functions may be affected.
Key takeaway
A credible result is a clearly defined next engineering decision, backed by observed conditions, stated assumptions, accountable interfaces and a plan to verify the remaining uncertainties. Well-planned FAT and SAT reduce ambiguity. They make clear what was proven, under what conditions, and what still needs attention before the system is relied upon by production.